Case studies

Two machines written off, both back in production, and the operators to run them

Three recent jobs, with the numbers. Clients are not named: we don't publish who we work for without their permission.

Rebuild · GDX-1 packer · 2023–2024

A 20% frame back in full production, 10 months faster than the OEM route

GDX-1 Series 100 frame in the client's warehouse before rebuild GDX-1 after rebuild, linked to the rest of the production line
Before: frame only, about 20% complete. After: 180 packs/min.
10 months
faster than the OEM route
180/min
packs, to factory spec

The problem

A cigarette manufacturer in East Java had a GDX-1 Series 100 frame sitting in its warehouse: about 20% complete, no control panel, no PLC, no electrics. Original parts were discontinued, and waiting for OEM parts would have taken far longer than the client could wait.

What we did

  • Sourced rare parts from suppliers in several countries.
  • Reverse-engineered and fabricated obsolete components to the original tolerances.
  • Built a new control panel and programmed the PLC from scratch.
  • Integrated the machine with the rest of the line as one production unit.
Full case study (Bahasa Indonesia) →

Rebuild · KDF filter rod maker · 2024

Idle for 10 years, producing again in 5 months

KDF filter rod maker before rebuild, with empty mounting points and missing assemblies KDF filter rod maker after rebuild, complete with digital controls
Before: incomplete frame. After: 3,000 rods/min.
5 months
frame to production
~10 years
idle before
3,000/min
rods after commissioning

The problem

A KDF filter rod maker had stood in a client's warehouse for almost ten years: incomplete, with sections and assemblies missing, written off as a production asset.

What we did

  • Mapped every gap between the machine as found and a working unit.
  • Restored and replaced the missing mechanical sections.
  • Rebuilt the electrics and converted the analog controls to digital.
  • Commissioned the machine and handed it over in production.
Full case study (Bahasa Indonesia) →

Training · high-speed maker line · 2026

Operator training the client re-ordered 3 days later

3 months
class + hands-on
3 days
until batch 2 was ordered
2×
participants in batch 2

The problem

One of our cigarette-factory clients wanted its operators to master a high-speed maker. They were experienced, but knowledge was uneven: when the machine stopped, only two or three senior people could deal with it.

What we did

  • Two weeks of classroom (10 days, 7 hours a day), taught by senior mechanics who overhaul these machines.
  • On-the-job training on the client's own line, with the trainer on the floor.
  • Every operator assessed while working at the machine, not only on paper.
  • A report telling management who is ready to run the machine alone and who still needs support.
Full case study (Bahasa Indonesia) →

Have a machine like these?

Send a few photos of it. We'll tell you honestly whether a rebuild makes sense.